A brand-new, two-floor, 80,000 sq ft retail store was opening in a mall in Natick, Massachusetts. Next Level Technology Group took it from an empty shell to opening day: the network closets, cabling, Wi-Fi, audio, phones and in-store touchscreen kiosks.
The challenge
The store was still being built while we worked. The crew made several trips to the site, coordinating with the construction team as the network rooms were built out and working with Verizon to get the circuits installed and routed to our demarc. Permanent electrical power also wasn’t finished in time, so we made an extra trip once it was in to install the computers and VoIP phones. The opening date never moved.
What we installed
- One MDF and two IDFs, each in a 12U wall cabinet with a patch panel, PoE switch and WattBox power, all interconnected
- More than 80 data drops across both floors
- 16 Wi-Fi access points
- Two-zone background audio on the customer’s amplifiers
- A VoIP phone system, with a SIP paging adapter that mutes the music during overhead pages
- One kiosk stand and two wall-mounted touchscreen kiosks, each running on a Chromebox
The result
Everything was tested and working before the doors opened, and the customer had a great opening weekend. With remote-managed WattBox power in every closet, equipment can be checked and rebooted without a trip to the store.
From empty shell to network closets





Kiosks, phones and the finished floor